Construction of 9-storied foundation 1st phase 4-storied with 2-basement “Savar New Market” in/c Civil, Sanitary, Electrical, Sub-station, Lift and Fire fighting works at Savar, Dhaka. Construction of 9-storied foundation 1st phase 4-storied with 2-basement “Savar New Market” in/c Civil, Sanitary, Electrical, Sub-station, Lift and Fire fighting works at Savar, Dhaka.
Completion date: 24.06.2013
Starting date: 25.12.2008
Plinth area per floor
Type of foundation: R.C.C Raft Foundation
Sub-station: 2 x 2000 KVA
Escalator: 6 Pairs
Lift: 3 Nos. each 1600 Kg. Capacity
Nature of work: Basement in/c foundation works, Super structure upto 3rd floor, Water supply and sanitary work, Electrical, Sub-station, Lift, Steel work in/c Dome, Air conditioning system, Firefighting & Fire detection work, Boundary work.