Balipara Bridge

Construction of 477.00 meter long (11×42.68m) PC Girder Bridge (Balipara Bridge) over the old Brahammaputra river at 13th km. of Trisal-Nandial-Tarail Road under Mymensingh Road Division during the year 2007-2008.

Description of Works

Bridge Length=477.00m(11x42.68m)

Width of the Bridge = 10.250m

Total Span = 11 Nos.

Navigation Clearance Height = 11.89m

Division-1: General and site facilities = Tk. 11,11,600/-

Division-2: Earth works  = Tk. 1,53,23,978.40

Division-3: Pavement works = Tk. 2,06,96,977.50

Division-4: Foundations Works :

a.  750mm dia pile quantity = 40 Nos., Pile length = 28m

b.  1000mm dia pile quantity = 130 Nos., Pile length = 21 to 25m

= Tk.  11,20,07,350.00

Division-5: Structure works :

a.  PC Girder quantity = 55 Nos., Length 42.68m = Tk:  23,68,06,062.24 

Division-6: Incidental = Tk.  1,31,52,169.80